Demo for Westgate Labs — all trials, clients and people are made up
All trials

WL26-015

Closed

Sclerotinia fungicide · Macquarie Plant Health

  1. Quote
    Sun, 25 Jan
  2. Approved
    Sun, 8 Feb
  3. Scheduled
    Sun, 1 Mar
  4. Started
    Sun, 8 Mar
  5. Field done
    Sun, 26 Apr
  6. Report
    Sun, 17 May
  7. Completed
    Sun, 24 May
  8. Closed
    Tue, 23 June

Plan v1 · Original plan · 23 June 2026 by Priya Raman

Week of
23 Feb2 Mar9 Mar16 Mar23 Mar30 Mar6 Apr13 Apr20 Apr27 Apr4 May11 May18 May25 May
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
DateTaskCalculated fromWindowWhoStatus
Sun, 22 FebChemical on handCompleted (date locked)on the dayPriya Ramancompleted
Sun, 1 MarSite readyCompleted (date locked)on the dayPriya Ramancompleted
Sun, 8 MarApplication 1Completed (date locked)on the daySam Nguyencompleted
Sun, 22 MarApplication 2Completed (date locked)on the daySam Nguyencompleted
Sun, 22 Mar0 DAT assessment (Application 2)Completed (date locked)on the daySam Nguyencompleted
Sun, 29 Mar7 DAT assessment (Application 2)Completed (date locked)until Mon, 30 MarSam Nguyencompleted
Sun, 5 Apr14 DAT assessment (Application 2)Completed (date locked)until Mon, 6 AprSam Nguyencompleted
Sun, 12 Apr21 DAT assessment (Application 2)Completed (date locked)until Mon, 13 AprSam Nguyencompleted
Sun, 26 Apr35 DAT assessment (Application 2)Completed (date locked)until Mon, 27 AprSam Nguyencompleted
Sun, 26 AprField work completeCompleted (date locked)on the dayPriya Ramancompleted
Sun, 17 MayReport draft dueCompleted (date locked)on the dayPriya Ramancompleted
Sun, 24 MayReport approvedCompleted (date locked)on the dayHelen Marshcompleted