WL26-014
CompletedPre-harvest desiccant · Bluegum AgChem
Invoice not issued
- QuoteWed, 15 Apr
- ApprovedWed, 29 Apr
- ScheduledWed, 20 May
- StartedWed, 27 May
- Field doneWed, 10 June
- ReportWed, 1 July
- CompletedWed, 8 July
- Closed—
Plan v1 · Original plan · 8 July 2026 by David Okafor
Week of
11 May18 May25 May1 June8 June15 June22 June29 June6 July
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
| Date | Task | Calculated from | Window | Who | Status |
|---|---|---|---|---|---|
| Wed, 13 May | Chemical on hand | Completed (date locked) | on the day | David Okafor | completed |
| Wed, 20 May | Site ready | Completed (date locked) | on the day | David Okafor | completed |
| Wed, 27 May | Application 1 | Completed (date locked) | on the day | Jess Walker | completed |
| Wed, 27 May | 0 DAT assessment (Application 1) | Completed (date locked) | on the day | Jess Walker | completed |
| Sat, 30 May | 3 DAT assessment (Application 1) | Completed (date locked) | until Sun, 31 May | Jess Walker | completed |
| Wed, 3 June | 7 DAT assessment (Application 1) | Completed (date locked) | until Thu, 4 June | Jess Walker | completed |
| Wed, 10 June | 14 DAT assessment (Application 1) | Completed (date locked) | until Thu, 11 June | Jess Walker | completed |
| Wed, 10 June | Field work complete | Completed (date locked) | on the day | David Okafor | completed |
| Wed, 1 July | Report draft due | Completed (date locked) | on the day | David Okafor | completed |
| Wed, 8 July | Report approved | Completed (date locked) | on the day | Helen Marsh | completed |