WL26-012
Report to be writtenCrown rot rotation study · Ridgeline Crop Sciences
Report overdue — client needs it for registration dossier — owner: Priya Raman
Urgent1 overduePayment overdue
- QuoteTue, 9 June
- ApprovedTue, 23 June
- ScheduledTue, 14 July
- StartedTue, 21 July
- Field doneTue, 1 Sept
- Report—
- Completed—
- Closed—
Plan v1 · Original plan · 2 Sept 2026 by Priya Raman
Week of
6 July13 July20 July27 July3 Aug10 Aug17 Aug24 Aug31 Aug7 Sept14 Sept21 Sept28 Sept
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
| Date | Task | Calculated from | Window | Who | Status |
|---|---|---|---|---|---|
| Tue, 7 July | Chemical on hand | Completed (date locked) | on the day | Priya Raman | completed |
| Tue, 14 July | Site ready | Completed (date locked) | on the day | Priya Raman | completed |
| Tue, 21 July | Application 1 | Completed (date locked) | on the day | Liam O'Connor | completed |
| Tue, 4 Aug | Application 2 | Completed (date locked) | on the day | Liam O'Connor | completed |
| Tue, 4 Aug | 0 DAT assessment (Application 2) | Completed (date locked) | on the day | Sam Nguyen | completed |
| Tue, 11 Aug | 7 DAT assessment (Application 2) | Completed (date locked) | until Wed, 12 Aug | Sam Nguyen | completed |
| Tue, 18 Aug | 14 DAT assessment (Application 2) | Completed (date locked) | until Wed, 19 Aug | Sam Nguyen | completed |
| Tue, 1 Sept | 28 DAT assessment (Application 2) | Completed (date locked) | until Wed, 2 Sept | Sam Nguyen | completed |
| Tue, 1 Sept | Field work complete | Completed (date locked) | on the day | Priya Raman | completed |
| Tue, 22 Sept | Report draft due | 21 days after Field work complete | on the day | Priya Raman | Overdue |
| Tue, 29 Sept | Report approved | 7 days after Report draft due | on the day | Helen Marsh | planned |