  1. Quote
    Sat, 4 July
  2. Approved
    Sat, 18 July
  3. Scheduled
    Sat, 8 Aug
  4. Started
    Sat, 15 Aug
  5. Field done
    Sat, 5 Sept
  6. Report
  7. Completed
  8. Closed

Plan v1 · Original plan · 5 Sept 2026 by David Okafor

Week of
3 Aug10 Aug17 Aug24 Aug31 Aug7 Sept14 Sept21 Sept28 Sept5 Oct
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
DateTaskCalculated fromWindowWhoStatus
Sat, 1 AugChemical on handCompleted (date locked)on the dayDavid Okaforcompleted
Sat, 8 AugSite readyCompleted (date locked)on the dayDavid Okaforcompleted
Sat, 15 AugApplication 1Completed (date locked)on the dayJess Walkercompleted
Sat, 15 Aug0 DAT assessment (Application 1)Completed (date locked)on the dayJess Walkercompleted
Sat, 22 Aug7 DAT assessment (Application 1)Completed (date locked)until Sun, 23 AugJess Walkercompleted
Sat, 29 Aug14 DAT assessment (Application 1)Completed (date locked)until Sun, 30 AugJess Walkercompleted
Sat, 5 Sept21 DAT assessment (Application 1)Completed (date locked)until Sun, 6 SeptJess Walkercompleted
Sat, 5 SeptField work completeCompleted (date locked)on the dayDavid Okaforcompleted
Sat, 26 SeptReport draft due21 days after Field work completeon the dayDavid Okaforplanned
Sat, 3 OctReport approved7 days after Report draft dueon the dayHelen Marshplanned