WL26-009
StartedThree-spray fungicide programme · Macquarie Plant Health
- QuoteSun, 19 July
- ApprovedSun, 2 Aug
- ScheduledSun, 23 Aug
- StartedSun, 30 Aug
- Field done—
- Report—
- Completed—
- Closed—
Plan v1 · Original plan · 30 Aug 2026 by Priya Raman
Week of
17 Aug24 Aug31 Aug7 Sept14 Sept21 Sept28 Sept5 Oct12 Oct19 Oct26 Oct2 Nov
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
| Date | Task | Calculated from | Window | Who | Status |
|---|---|---|---|---|---|
| Sun, 16 Aug | Chemical on hand | Completed (date locked) | on the day | Priya Raman | completed |
| Sun, 23 Aug | Site ready | Completed (date locked) | on the day | Priya Raman | completed |
| Sun, 30 Aug | Application 1 | Completed (date locked) | on the day | Sam Nguyen | completed |
| Sun, 13 Sept | Application 2 | Completed (date locked) | on the day | Sam Nguyen | completed |
| Sun, 13 Sept | 0 DAT assessment (Application 2) | Completed (date locked) | on the day | Jess Walker | completed |
| Mon, 14 Sept | 1 DAT assessment (Application 2) | Completed (date locked) | on the day | Jess Walker | completed |
| Thu, 17 Sept | 4 DAT assessment (Application 2) | Completed (date locked) | until Fri, 18 Sept | Jess Walker | completed |
| Sun, 20 Sept | 7 DAT assessment (Application 2) | Completed (date locked) | until Mon, 21 Sept | Jess Walker | completed |
| Sun, 27 Sept | 14 DAT assessment (Application 2) | 14 DAT from Application 2 | until Mon, 28 Sept | Jess Walker | planned |
| Sun, 27 Sept | Application 3 | 14 days after Application 2 | on the day | Sam Nguyen | planned |
| Sun, 4 Oct | 21 DAT assessment (Application 2) | 21 DAT from Application 2 | until Mon, 5 Oct | Jess Walker | planned |
| Sun, 4 Oct | Field work complete | Same day as 21 DAT assessment (Application 2) | on the day | Priya Raman | planned |
| Sun, 25 Oct | Report draft due | 21 days after Field work complete | on the day | Priya Raman | planned |
| Sun, 1 Nov | Report approved | 7 days after Report draft due | on the day | Helen Marsh | planned |