WL26-008
StartedPost-emergent grass selective · Bluegum AgChem
1 overdue
- QuoteMon, 3 Aug
- ApprovedMon, 17 Aug
- ScheduledMon, 7 Sept
- StartedMon, 14 Sept
- Field done—
- Report—
- Completed—
- Closed—
Plan v1 · Original plan · 14 Sept 2026 by David Okafor
Week of
31 Aug7 Sept14 Sept21 Sept28 Sept5 Oct12 Oct19 Oct26 Oct2 Nov
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
| Date | Task | Calculated from | Window | Who | Status |
|---|---|---|---|---|---|
| Mon, 31 Aug | Chemical on hand | Completed (date locked) | on the day | David Okafor | completed |
| Mon, 7 Sept | Site ready | Completed (date locked) | on the day | David Okafor | completed |
| Mon, 14 Sept | Application 1 | Completed (date locked) | on the day | Sam Nguyen | completed |
| Mon, 14 Sept | 0 DAT assessment (Application 1) | Completed (date locked) | on the day | Jess Walker | completed |
| Tue, 15 Sept | 1 DAT assessment (Application 1) | Completed (date locked) | on the day | Jess Walker | completed |
| Fri, 18 Sept | 4 DAT assessment (Application 1) | Completed (date locked) | until Sat, 19 Sept | Jess Walker | completed |
| Mon, 21 Sept | 7 DAT assessment (Application 1) | 7 DAT from Application 1 | until Tue, 22 Sept | Jess Walker | Overdue |
| Mon, 28 Sept | 14 DAT assessment (Application 1) | 14 DAT from Application 1 | until Tue, 29 Sept | Jess Walker | planned |
| Mon, 28 Sept | Application 2 | 14 days after Application 1 | on the day | Sam Nguyen | planned |
| Mon, 5 Oct | 21 DAT assessment (Application 1) | 21 DAT from Application 1 | until Tue, 6 Oct | Jess Walker | planned |
| Mon, 5 Oct | Field work complete | Same day as 21 DAT assessment (Application 1) | on the day | David Okafor | planned |
| Mon, 26 Oct | Report draft due | 21 days after Field work complete | on the day | David Okafor | planned |
| Mon, 2 Nov | Report approved | 7 days after Report draft due | on the day | Helen Marsh | planned |