WL26-007
ScheduledFungicide programme — net blotch · Ridgeline Crop Sciences
Disease pressure rising — client asked to start this week — owner: Tom Brennan
Urgent
- QuoteFri, 14 Aug
- ApprovedFri, 28 Aug
- ScheduledFri, 18 Sept
- Started—
- Field done—
- Report—
- Completed—
- Closed—
Plan v1 · Original plan · 18 Sept 2026 by Tom Brennan
Week of
14 Sept21 Sept28 Sept5 Oct12 Oct19 Oct26 Oct2 Nov9 Nov16 Nov
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
| Date | Task | Calculated from | Window | Who | Status |
|---|---|---|---|---|---|
| Sun, 13 Sept | Chemical on hand | Completed (date locked) | on the day | Tom Brennan | completed |
| Sun, 20 Sept | Site ready | Completed (date locked) | on the day | Tom Brennan | completed |
| Sun, 27 Sept | Application 1 | Fixed date | on the day | Sam Nguyen | planned |
| Sun, 27 Sept | 0 DAT assessment (Application 1) | 0 DAT from Application 1 | on the day | Liam O'Connor | planned |
| Sun, 4 Oct | 7 DAT assessment (Application 1) | 7 DAT from Application 1 | until Mon, 5 Oct | Liam O'Connor | planned |
| Sun, 11 Oct | 14 DAT assessment (Application 1) | 14 DAT from Application 1 | until Mon, 12 Oct | Liam O'Connor | planned |
| Sun, 18 Oct | 21 DAT assessment (Application 1) | 21 DAT from Application 1 | until Mon, 19 Oct | Liam O'Connor | planned |
| Sun, 18 Oct | Application 2 | 21 days after Application 1 | on the day | Sam Nguyen | planned |
| Sun, 18 Oct | Field work complete | Same day as 21 DAT assessment (Application 1) | on the day | Tom Brennan | planned |
| Sun, 8 Nov | Report draft due | 21 days after Field work complete | on the day | Tom Brennan | planned |
| Sun, 15 Nov | Report approved | 7 days after Report draft due | on the day | Helen Marsh | planned |