Scheduled

Fungicide programme — net blotch · Ridgeline Crop Sciences

Disease pressure rising — client asked to start this week — owner: Tom Brennan

Urgent
  1. Quote
    Fri, 14 Aug
  2. Approved
    Fri, 28 Aug
  3. Scheduled
    Fri, 18 Sept
  4. Started
  5. Field done
  6. Report
  7. Completed
  8. Closed

Plan v1 · Original plan · 18 Sept 2026 by Tom Brennan

Week of
14 Sept21 Sept28 Sept5 Oct12 Oct19 Oct26 Oct2 Nov9 Nov16 Nov
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
DateTaskCalculated fromWindowWhoStatus
Sun, 13 SeptChemical on handCompleted (date locked)on the dayTom Brennancompleted
Sun, 20 SeptSite readyCompleted (date locked)on the dayTom Brennancompleted
Sun, 27 SeptApplication 1Fixed dateon the daySam Nguyenplanned
Sun, 27 Sept0 DAT assessment (Application 1)0 DAT from Application 1on the dayLiam O'Connorplanned
Sun, 4 Oct7 DAT assessment (Application 1)7 DAT from Application 1until Mon, 5 OctLiam O'Connorplanned
Sun, 11 Oct14 DAT assessment (Application 1)14 DAT from Application 1until Mon, 12 OctLiam O'Connorplanned
Sun, 18 Oct21 DAT assessment (Application 1)21 DAT from Application 1until Mon, 19 OctLiam O'Connorplanned
Sun, 18 OctApplication 221 days after Application 1on the daySam Nguyenplanned
Sun, 18 OctField work completeSame day as 21 DAT assessment (Application 1)on the dayTom Brennanplanned
Sun, 8 NovReport draft due21 days after Field work completeon the dayTom Brennanplanned
Sun, 15 NovReport approved7 days after Report draft dueon the dayHelen Marshplanned