Demo for Westgate Labs — all trials, clients and people are made up
All trials

WL26-005

Ready to schedule

Biological seed dressing · Lachlan Biologicals

  1. Quote
    Sat, 22 Aug
  2. Approved
    Sat, 5 Sept
  3. Scheduled
  4. Started
  5. Field done
  6. Report
  7. Completed
  8. Closed

Plan v1 · Original plan · 19 Sept 2026 by Tom Brennan

Week of
28 Sept5 Oct12 Oct19 Oct26 Oct2 Nov9 Nov16 Nov23 Nov30 Nov7 Dec14 Dec21 Dec
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
DateTaskCalculated fromWindowWhoStatus
Mon, 28 SeptChemical on hand14 days before Application 1on the dayTom Brennanplanned
Mon, 5 OctSite ready7 days before Application 1on the dayTom Brennanplanned
Mon, 12 OctApplication 1Fixed dateon the dayLiam O'Connorplanned
Mon, 12 Oct0 DAT assessment (Application 1)0 DAT from Application 1on the dayLiam O'Connorplanned
Mon, 26 Oct14 DAT assessment (Application 1)14 DAT from Application 1until Tue, 27 OctLiam O'Connorplanned
Mon, 9 Nov28 DAT assessment (Application 1)28 DAT from Application 1until Tue, 10 NovLiam O'Connorplanned
Mon, 23 Nov42 DAT assessment (Application 1)42 DAT from Application 1until Tue, 24 NovLiam O'Connorplanned
Mon, 23 NovField work completeSame day as 42 DAT assessment (Application 1)on the dayTom Brennanplanned
Mon, 14 DecReport draft due21 days after Field work completeon the dayTom Brennanplanned
Mon, 21 DecReport approved7 days after Report draft dueon the dayHelen Marshplanned