WL26-004
Awaiting chemicalBroadleaf weed herbicide rates · Ridgeline Crop Sciences
Product sample not yet received from client — owner: David Okafor
Blocked
- QuoteSun, 30 Aug
- ApprovedSun, 13 Sept
- Scheduled—
- Started—
- Field done—
- Report—
- Completed—
- Closed—
Plan v1 · Original plan · 20 Sept 2026 by David Okafor
Week of
5 Oct12 Oct19 Oct26 Oct2 Nov9 Nov16 Nov23 Nov30 Nov7 Dec14 Dec
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
| Date | Task | Calculated from | Window | Who | Status |
|---|---|---|---|---|---|
| Sun, 4 Oct | Chemical on hand | 14 days before Application 1 | on the day | David Okafor | planned |
| Sun, 11 Oct | Site ready | 7 days before Application 1 | on the day | David Okafor | planned |
| Sun, 18 Oct | Application 1 | Fixed date | on the day | Jess Walker | planned |
| Sun, 18 Oct | 0 DAT assessment (Application 1) | 0 DAT from Application 1 | on the day | Jess Walker | planned |
| Sun, 25 Oct | 7 DAT assessment (Application 1) | 7 DAT from Application 1 | until Mon, 26 Oct | Jess Walker | planned |
| Sun, 1 Nov | 14 DAT assessment (Application 1) | 14 DAT from Application 1 | until Mon, 2 Nov | Jess Walker | planned |
| Sun, 15 Nov | 28 DAT assessment (Application 1) | 28 DAT from Application 1 | until Mon, 16 Nov | Jess Walker | planned |
| Sun, 15 Nov | Field work complete | Same day as 28 DAT assessment (Application 1) | on the day | David Okafor | planned |
| Sun, 6 Dec | Report draft due | 21 days after Field work complete | on the day | David Okafor | planned |
| Sun, 13 Dec | Report approved | 7 days after Report draft due | on the day | Helen Marsh | planned |